A project requires many different resources for its execution. thus, a project manager has requested a new part from an out-of-state supplier. the supplier promises to ship the part within 24 hours, but due to a trade blockage, the shipment may take 3 to 6 business days to deliver. on the other hand, a local supplier can deliver the part within 4 business days. the project manager wants to execute the project smoothly without any delay. what's the minimum number of business days within which the project manager can receive the part?

Respuesta :

Your answer is:

4 business days