Based on the linear program technique, and the available option, the statement that is not a decision variable when formulating the project crashing problem as a linear program is the early start times of all activities.
The term linear programming is used to describe the mathematical modeling technique in which a linear function is maximized or minimized when subjected to various constraints.
Generally, the linear program technique has been useful for guiding quantitative decisions in business planning, industrial engineering, and—to a lesser extent—the social and physical sciences.
There are a lot of factors to consider when using linear programming for project-crashing programs. Some of the factors are the following:
Generally, the early start time of all activities doesn't affect decision-making in formulating the project crashing problem because this is the starting point, and it won t affect the project completion duration.
Hence, in this case, it is concluded that the correct answer is option A. "the early start times of all activities."
Learn more about linear program here: https://brainly.com/question/14309521