As a construction estimator you estimate the cost of bathroom remodels for a general contractor one client asks for an estimate for two bathroom remodels. you estimate it will cost $20,000 for both remodels when the project is finished all the supplies came in at the estimated budget except for two vanities which were each $100 less than the budgeted amount what was the difference between the actual cost and estimated cost for the two bathroom remodels

Respuesta :

For two bathroom remodel estimate budget is $[tex]20000[/tex] for both remodels. when the project is finished all the supplies came in at the estimated budget except for two vanities which were each $[tex]100[/tex] less than the budgeted .So the actual cost of two bathroom remodel is $ [tex]19800[/tex] and the different of actual and expected budgets is $[tex]200[/tex]

How can we find the actual costing of the bathroom remodel ?

Expected estimate budget of two bathroom's remodel is $[tex]20000[/tex]

So budget of one bathroom remodel is

[tex]20000/2\\=10000[/tex]

All supplies are come except for two vanities which were each $[tex]100[/tex]

So for two bathroom remodels

[tex]=2*100\\=200[/tex]

So the actual cost of remodel of both bathroom is

[tex]=20000-200\\=19800[/tex]

And difference between actual and estimated cost is

[tex]=20000-19800\\=200[/tex]

Learn more about the actual and estimated cost here :

https://brainly.com/question/28049908

#SPJ4