The operations manager of a body and paint shop has five cars to schedule for repair. He would like to minimize the makespan to complete all work on these cars. Each car requires body work prior to painting. The estimates of the times required to do the body and paint work on each are as follows:

Body work Paint
Car (hrs) (hrs)
A 10 2
B 5 4
C 7 5
D 3 6
E 1 7

Where in the optimum sequence should car A be scheduled?
a. first
b. second
c. third
d. fourth
e. fifth

Respuesta :

Answer:

e. fifth

Explanation:

Car A should be scheduled as fifth in the sequence to repair and repaint. The Car A will take 10 hours for repair work which is highest of all other cars. The paint work is however lower than all other cars but since the repair work is to be done prior to repainting the car A should be schedule in the last.