Santoyo Corporation keeps careful track of the time required to fill orders. Data concerning a particular order appear below: Hours Wait time 28.0 Process time 1.0 Inspection time 0.4 Move time 3.2 Queue time 5.1 The delivery cycle time was: (Round your intermediate calculations to 1 decimal place.) Multiple Choice 36.3 hours 8.3 hours 37.7 hours 3.2 hours

Respuesta :

Answer:

37.7 hours

Explanation:

Calculation to determine what The delivery cycle time was:

Using this formula

Delivery cycle time=Wait time +Throughput time

Where,

Wait time=28.0

Throughput time=Process time 1.0+ Inspection time 0.4+ Move time 3.2 +Queue time 5.1=9.7

Let plug in the formula

Delivery cycle time=28.0+9.7

Delivery cycle time=37.7

Therefore Delivery cycle time was 37.7