Answer: See explanation
Explanation:
The number of kanban cards that are needed can be calculated below:
Average demand, D = 16
Lead time, L = 2 hours
Safety stock, S = 12.5% = 0.125
Catalytic converters, C = 10
Using the formula, =DL(1+S) / C
= 16×2(1 + 0.125) / 10
= 32(1.125) / 10
= 36 / 10
= 3.6
= 4 approximately
Therefore, 4 kanban cards are needed.