Answer:
Jackpot Mining Company
1. Journal Entries to
a) record the acquisition cost of ths mine:
Debit Investment in Copper Mine $1,750,000
Credit Cash $1,750,000
To record the cost of acquiring the mining site
Debit Investment in Copper Mine $750,000
Credit Cash $750,000.
To record the cost of preparing the mine site.
Debit Investment in Copper Mine $390,844
Credit Restoration Liability $390,844
To record the provision for mine restoration liability.
b) the purchase of equipment:
July 1, 2021
Debit Equipment $270,000
Credit Cash $270,000
To record the purchase of equipment.
Explanation:
a) Data and Analysis:
2021 Investment in Copper Mine $1,750,000 Cash $1,750,000
2021 Investment in Copper Mine $750,000 Cash $750,000
Restoration cost:
Cash Outflow Probability Expected Cost
1 $ 450,000 15 % $67,500
2 550,000 45 % 247,500
3 750,000 40 % 300,000
Expected restoration cost = $615,000
Adjusted risk-free interest rate = 12%
Mining period before restoration = 4 years
PV of restoration cost = $390,844
N (# of periods) 4
I/Y (Interest per year) 12
PMT (Periodic Payment) 0
FV (Future Value) $615,000
Results
PV = $390,843.62
Total Interest $224,156.38
Purchase of new equipment"
July 1, 2021 Equipment $270,000 Cash $270,000
Total cost of copper mine:
Acquisition cost $1,750,000
Additional cost 750,000
Restoration cost 390,844
Total cost of mine $2,890,844