Respuesta :
Answer:
24.8 per hour
Explanation:
There are 3 workers and hence are three workstations. Consecutive activities are assigned to each workstation such that workload is as uniform as possible
Hence the time in each workstation (WS) is,
WS1 = 45+55+15 = 115 seconds
WS2 = 25+50+5+30 = 110 seconds
WS3 = 95+50 = 145 seconds
Workstation 3 has the highest processing time and hence is the bottleneck and determines the capacity of the process
Therefore capacity = 1/145 per second = 3600/145 per hour = 24.8 per hour
There are 3 workers and hence are three workstations. Consecutive activities are assigned to each workstation such that workload is as uniform as possible
Hence, the time in each workstation (WS) is,
WS1 = 45+55+15 = 115 seconds
WS2 = 25+50+5+30 = 110 seconds
WS3 = 95+50 = 145 seconds
Workstation 3 has the highest processing time and hence is the bottleneck and determines the capacity of the process,
Therefore, capacity = 1/145 per second = 3600/145 per hour
= 24.8 per hour
What is capacity?
The capacity is the ability to contain or deal with something. It describes your ability to do something or the amount something can hold.
If your bird cage is at full capacity, you can't stuff one more feathered friend in there without causing birdie claustrophobia.
Thus, the capacity of this process in units per hour is 24.8 per hour