Martin Inc. began construction on a building in 2020 and paying a construction company $600,000 in 2020. Martin also had avoidable interest of $30,000 and actual interest of $100,000 in 2020. Martin financed the construction with a $1,000,000, 10% loan specific to the project. The project was completed on September 30, 2021. Additional expenditures in 2021 were as follows:

Feb. 28 $90,000
Apr. 30 180,000
Jul. 1 36,000
Sept. 30 64,000

Required:
Once completed, how much is capitalized in Martin’s Building account? Show all your work.