Calculate the unit rate for Machine A and Machine B. Determine which is the greater rate (Below).

Machine A covers 5/8 square feet in 1/4 hour or Machine B covers 2/3 square feet in 1/5 hour.

Respuesta :

Answer:

Unit Rate of Machine A = 2.5 square feet per hour

Unit Rate of Machine B = 3.333 square feet per hour.

The unit rate of Machine B is greater than unit rate of machine A.

Step-by-step explanation:

The unit rates for both machines need to be calculated first.

The unit rate will be calculated as:

[tex]Unit\ rate = \frac{Area\ covered}{Time}[/tex]

For Machine A:

Area Covered = 5/8

Time = 1/4

The unit rate will be:

[tex]U_A = \frac{\frac{5}{8} }{\frac{1}{4} } \\Using\ rule => \frac{\frac{a}{b} }{\frac{c}{d} } = \frac{a}{b} * \frac{d}{c}\\=\frac{5}{8} * 4 \\= \frac{5}{2} = 2.5\ square\ feet\ per\ hour[/tex]

For Machine B:

Area Covered = 2/3

Time = 1/5

[tex]U_B = \frac{\frac{2}{3}}{\frac{1}{5}}\\= \frac{2}{3} * \frac{5}\\= \frac{10}{3}\\= 3.33...\ square\ feet\ per\ hour[/tex]

As it can be seen that unit rate for Machine B is greater than Unit Rate of Machine A.

Hence,

Unit Rate of Machine A = 2.5 square feet per hour

Unit Rate of Machine B = 3.333 square feet per hour.

The unit rate of Machine B is greater than unit rate of machine A.