Answer:
$605
Step-by-step explanation:
For the computation of manufacturing overhead first we need to compute plantwide predetermined overhead which is shown below:-
Plantwide predetermined overhead rate = Estimated manufacturing overhead cost ÷ Direct labor hours
= $3,080,000 ÷ 112,000
= $27.5
manufacturing overhead to be applied = Direct labor hours × Plantwide predetermined overhead rate
= 22 × $27.5
= $605