During March, Patt, Inc. purchases and uses 8,800 pounds of materials costing $35,640 to make 4,000 tiles. Patt's standard material cost per tile is $8 (2 pounds of material × $4.00).

Respuesta :

Answer and Explanation:

The computation is shown below:

Total material cost variance

= (Standard quantity × standard price) - (actual quantity × actual price)

= (4,000 tiles × 2 pounds of material × $4) - (8,800 pounds × $35,640 ÷ 8,800 pounds)

= (8,000 pounds × $4) - ($8,800 pounds × $4.05)

= $3,640 unfavorable

For material price variance

= Actual Quantity × (Standard Price - Actual Price)

= 8,800 × ($4 - $4.05)

= $440 unfavorable

For material quantity variance

= Standard Price × (Standard Quantity - Actual Quantity)

= $4 × (8,000 pounds - 8,800 pounds)

= $3,200 unfavorable

The favorable variance is that in which the standard cost is more than the actual cost and the inverse goes to unfavorable variance