The milestone schedule in the project charter: ​ a. is a high-level plan that indicates a few significant accomplishments anticipated over the life of the project. b. is a detailed schedule that shows the planned duration for every activity in the project. c. is a summary-level schedule that shows how major project tasks are sequenced. d. is a schedule that provides detailed data for when each project activity should begin.

Respuesta :

Answer:

The correct answer is letter "A": is a high-level plan that indicates a few significant accomplishments anticipated over the life of the project.

Explanation:

In project management, a milestone schedule lists different activities necessary to accomplish certain goals. This tool is useful for managers to measure the progress of a project and determine if there are delays. In the schedule milestone, executives mark the completion of certain activities resulting from the operations of the business establishing a formal ending.

Usually, this schedule is helpful to validate the performance of work with shorter deadlines that do not represent major accomplishments for the project.

ACCESS MORE
ACCESS MORE
ACCESS MORE
ACCESS MORE