Barbara Flynn is in charge of maintaining hospital supplies at General Hospital. During the past​ year, the mean lead time demand for bandage​ BX-5 was 75 ​(and was normally​ distributed). Furthermore, the standard deviation for​ BX-5 was 6. Ms. Flynn would like to maintain a 95​% service level. a) what safety stock level do you recommend for BX-5 b) what is the appropriate reorder point?

Respuesta :

Answer:

a)  10

b)  85

Explanation:

a)

The safety stock is gotten by multiplying the standard deviation with the appropriate z value (demand and service level).

THe z coefficient of service level of 95% is 1.64

So we multiply the SD (standard deviation) with 1.64

Safety Stock = 6 * 1.64 = 9.84 = 10

b)

Now, the reorder point.

Reorder Point = Lead Time Demand + Safety Stock

It is already given that Lead TIme Demand is 75 and we found Safety Stock to be 10, so:

Reorder Point = 75 + 10 = 85

The Safety Stock is 10. and the Reorder Point = 85.

a)  Safety stock = Standard deviation * Appropriate z value (demand and service level).

  • The z coefficient of service level of 95% is 1.64
  • We are given that SD is 6

Safety Stock = 6 * 1.64

Safety Stock = 9.84

Safety Stock = 10

b) Reorder Point = Lead Time Demand + Safety Stock

Given Information

Lead TIme Demand = 75

Safety Stock = 10

Reorder Point = 75 + 10

Reorder Point = 85

See similar solution here

brainly.com/question/15242972