Which of the following is NOT part of the project​ controlling?
a. shifting resources to where they are needed most
b. sequencing and allotting time to all project activities
c. close monitoring of​ resources, costs,​ quality, and budgets
d. using a feedback loop to revise the project plan

Respuesta :

Answer:

b. sequencing and allotting time to all project activities

Explanation:

' Project Controls are data collection, data management and predictive methods used to forecast, interpret and proactively control the time and cost results of a project or program; by communicating information in ways that enable effective management and decision-making.

So, a, c and  d are statements are a part of project controlling but b that is

sequencing and allotting time to all project activities  is not a part of project controlling.