Answer:
The risk-adjusted project cost of capital for a low-risk project in the HR division = 10% - 2% = 8%.
The correct answer is 8%
Explanation:
Since the overall cost of capital is 10% and the project is less risky, the company needs to deduct 2% return from the average return of 10%.