Additional information
Loading Method Single Pusher Tandem Pusher
Back-Track 1.5 1.4
Chain or Shuttle 1.0 0.9
Answer:
(a) 3 back-trucks and 2 chains
(b) 2491 BCY/hr
Explanation:
(a)
The number of scrapers per pusher
[tex]Back-track=\frac {7}{1.5}=4.667[/tex]
[tex]Chain=\frac {7}{1}=7[/tex]
Number of pushers needed
[tex]Back-truck=\frac {11}{4.667}=2.357\approx 3[/tex]
[tex]Chain=\frac {11}{7}=1.57\approx 2[/tex]
(b)
Production=(Number of pushers* Number of scrappers* Production per scrapper)/ Required number of pushers
[tex]Production=\frac {1}{1.4}\times 11 \times 317 BCY/hr= 2490.7\approx 2491 BCY/hr[/tex]