Hillside Homes, Inc., and Ideal Builders, Inc., enter into a construction contract that includes six pages of detailed calculations. Later Hillside, whose project manager compiled the figures, discovers that some numbers were multiplied incorrectly, but Ideal refuses to make changes. A court would most likely
Choose one answer.
a. award damages to Hillside for the mistakes.
b. award damages to Ideal for the mistakes.
c. allow the parties to rescind the contract.
d. enforce the contract without requiring changes.