Answer:
A) $56,000
Explanation:
Provided information,
Total overheads
Factory maintenance = $96,000
Rent on factory building = $180,000
Utility = $44,000
Total overheads = $320,000
Total labor hours of each product
Product X = 700 [tex]\times[/tex] 2 = 1,400 hours
Product Y = 2,000 [tex]\times[/tex] 3.3 = 6,600 hours
Total hours = 8,000
Overheads allocated to product X based on labor hours = [tex]\frac{320,000}{8,000} \times\: 1,400 = 56,000[/tex]
Therefore correct option is
A) $56,000