Answer: The correct answer is the risk level of the project.
Explanation: When a company is deciding on the cost of capital of a new project they need to determine where the risk level is in comparison to their normal operations. The company will know what their WACC (weighted average cost of capital) is. If the new project is similar in risk to the other operations the company will know that it will be accurate to use the existing WACC of the business.