You get a call from a Program Manager. His program has been experiencing difficulty getting funding. He nearly had to stop work on his program last quarter due to a lack of funds. He is facing the same situation this quarter. He has been trying to locate funding and thinks he has come up with a solution. He explains to you that he can get enough procurement funding to cover the effort for the rest of the year. Previously, the effort was funded with RDT&E funding. As the PCO, what issues would you consider before taking action to obligate the procurement funds?