On 3 Sep 08 the CO awarded a contract for computer purchases using FY08 O&M (3400) funds. The computers were to be delivered upon completion of a new building expected sometime early in CY 09, but the contractor could have delivered the computers almost immediately upon contract award. Are there any fiscal issues here?